Data Table for Street Resurface/Water Main Project Coordination | ||||
Task Name | Task Status | Assigned To | Start Date | End Date |
---|---|---|---|---|
Project development | New Item | 01/02/2013 | 02/28/2013 | |
Budget approval | New Item | 03/01/2013 | 03/15/2013 | |
Project engineering | New Item | 03/16/2013 | 03/31/2013 | |
Bidding process | New Item | 04/01/2013 | 05/10/2013 | |
Construction | New Item | 05/11/2013 | 05/31/2013 | |
Complete Street Overlay | On Schedule | 04/01/2014 | 06/30/2014 |