Data Table for Street Resurface/Water Main Project Coordination

Task NameTask StatusAssigned ToStart
Date
End
Date
Project development
New Item
01/02/201302/28/2013
Budget approval
New Item
03/01/201303/15/2013
Project engineering
New Item
03/16/201303/31/2013
Bidding process
New Item
04/01/201305/10/2013
Construction
New Item
05/11/201305/31/2013
Complete Street Overlay
On Schedule
04/01/201406/30/2014