Data Table for Fiber Optic Consortium

Task NameTask StatusAssigned ToStart
Date
End
Date
Plan routing for new fiber lines to City facilities
New Item
03/03/201404/07/2014
Train staff to handle and install fiber cable
New Item
04/08/201404/30/2014
Procure fiber cable, equipment and supplies
New Item
05/05/201405/30/2014
Install fiber cable
New Item
06/02/201409/30/2014
Make final connections & assign IP addresses
New Item
10/06/201412/19/2014
Select 3 new Consortium members
New Item
01/05/201501/30/2015
Execute agreements
New Item
02/02/201503/31/2015
Plan fiber routing to new members
New Item
06/30/201507/31/2015
Procure fiber cable, equipment and supplies
New Item
09/01/201509/30/2015
Install fiber cable
New Item
10/01/201512/18/2015
Make final connections & assign IP addresses
New Item
01/04/201603/25/2016