Data Table for Fiber Optic Consortium | ||||
Task Name | Task Status | Assigned To | Start Date | End Date |
---|---|---|---|---|
Plan routing for new fiber lines to City facilities | New Item | 03/03/2014 | 04/07/2014 | |
Train staff to handle and install fiber cable | New Item | 04/08/2014 | 04/30/2014 | |
Procure fiber cable, equipment and supplies | New Item | 05/05/2014 | 05/30/2014 | |
Install fiber cable | New Item | 06/02/2014 | 09/30/2014 | |
Make final connections & assign IP addresses | New Item | 10/06/2014 | 12/19/2014 | |
Select 3 new Consortium members | New Item | 01/05/2015 | 01/30/2015 | |
Execute agreements | New Item | 02/02/2015 | 03/31/2015 | |
Plan fiber routing to new members | New Item | 06/30/2015 | 07/31/2015 | |
Procure fiber cable, equipment and supplies | New Item | 09/01/2015 | 09/30/2015 | |
Install fiber cable | New Item | 10/01/2015 | 12/18/2015 | |
Make final connections & assign IP addresses | New Item | 01/04/2016 | 03/25/2016 |