Review engineering study with MPPA staff | New Item | 02/03/2014 | 02/28/2014 | |
Review study with proposed member communities | New Item | 03/03/2014 | 03/28/2014 | |
Review engineering study with MPPA Board of Commissioners | New Item | 04/01/2014 | 04/25/2014 | |
If viable program, secure Hart Power Board & City Council approval to join MPPA project committee | New Item | 05/05/2014 | 05/30/2014 | |
Join MPPA Full-Requirements Project | New Item | 06/02/2014 | 06/27/2014 | |
Negotiate master project agreement with MMPA | New Item | 07/01/2014 | 10/31/2014 | |
Prepare implementation plan (by MPPA) | New Item | 11/03/2014 | 02/27/2015 | |
Begin Full-Requirements Project | New Item | 03/02/2015 | 03/31/2015 |