Data Table for Full-Requirements Electric Power Supply

Task NameTask StatusAssigned ToStart
Date
End
Date
Review engineering study with MPPA staff
New Item
02/03/201402/28/2014
Review study with proposed member communities
New Item
03/03/201403/28/2014
Review engineering study with MPPA Board of Commissioners
New Item
04/01/201404/25/2014
If viable program, secure Hart Power Board & City Council approval to join MPPA project committee
New Item
05/05/201405/30/2014
Join MPPA Full-Requirements Project
New Item
06/02/201406/27/2014
Negotiate master project agreement with MMPA
New Item
07/01/201410/31/2014
Prepare implementation plan (by MPPA)
New Item
11/03/201402/27/2015
Begin Full-Requirements Project
New Item
03/02/201503/31/2015